Solution:
  Continuous installation system with
  four treatment zones
  Zone 1 for positioning the carriers with the parts
  and cleaning the teeth using rotating
  high-pressure nozzles
  Washing and rinsing in conventional
  multi-stage process
  Circulating air drying at air speeds
  up to 60 m/sec


HTK GmbH
Kirchstraße 26
D-67377 Gommersheim
Telefon: 0 63 27 / 96 05 32
Telefax: 0 63 27 / 96 05 33
info@htk-reinigungsanlagen.de

The job involved the following tasks:
  Cleaning machined parts
  Cleaning after blasting
  Defined high-pressure cleaning of the narrow
  internal and external gear toothing
  Parts positioning during transport
  Avoiding any damage as the parts are conveyed
  through the machine
  Loading and unloading to be carried out by
  one operator
  Compact design
  Easy access to all system components